Upgrade Cluster Node from 2012 core to full GUI

$
0
0

Hi,

I have 5 node Windows 2012 cluster and one of the nodes is Server core.

I would like to add the GUI to this and was wondering if I can do this while it is still a member of the cluster, or do the guest VM's need to be migrated to another node before evicting it from the cluster?

I also have 2 VMs powered off on this node as they simply WILL NOT migrate to other nodes, will these be fine to remain powered off on the node will carrying out the above?

Regards

Leon