Howdy,
We have a 5 node (soon to be 6) Hyper-V cluster. We currently have enough resources in them that we could run all our VMs on only 3 nodes. Is there any way to tell CAU to patch 2 nodes at a time instead of only doing 1? We're trying to cut down the time it takes to patch the clusters but I don't know if it can handle that or not.
If not, are there any powershell type scripts that we could look into that can handle an entire patch cycle with migrating, patching, rebooting, etc?