moving active node resources to the inactive node

$
0
0

We have a 2 node , majority disk, Windows 2008R2 failover cluster.   The active node is currently showing all resources and services on node A.   Node B is the inactive node.    we are about to perform a DataCenter shutdown test.   Our application manager would like us to make Node B inactive during the DataCenter Shutdown test but he believes we can make Node B active if we do it this way:

1.  power down Node B (inactive node)

2. power down Node A (active node)

3. power up Node A (active node)

4. power up Node B (inactive node)

By doing this way, he believes Node B will automatically become the Active node.

I do not believe this is correct.   I believe it has to failover to get Node B active.  So, my proposal is:

1.  power down Node A (active node)  This should cause a failover of resources and services to Node B

2. Once all resources and services are on Node B, power Node B down.   Now, both nodes are powered down and Node B is holding the cluster resources and services and is the Active node.

3.  Power up Node B (now the new Active node)

4. Power up Node A ( the new inactive node)

Which is correct?